This project will improve the comfort of the students and staff and allow the implementation of more classrooms.
Tentative timeline of the project:
- Spring 2016: Start of Design Development by Consultants
- Summer 2017: Demolition of Staff Quarters building
- Summer 2019: Completion of outdoor improvement of existing building
- Summer 2020: Completion of new BX building and related modification of existing building.